MNT-07: Maintain Configuration Control During Maintenance
Mechanisms exist to maintain proper physical security and configuration control over technology assets awaiting service or repair.
Control Question: Does the organization maintain proper physical security and configuration control over technology assets awaiting service or repair?
General (15)
| Framework | Mapping Values |
|---|---|
| MITRE ATT&CK 10 | T1059.002, T1204.003, T1505, T1505.001, T1505.002, T1505.004, T1546.006, T1554, T1601, T1601.001, T1601.002 |
| NIST 800-53 R5 (source) | SR-11(2) |
| NIST 800-53B R5 (low) (source) | SR-11(2) |
| NIST 800-53B R5 (moderate) (source) | SR-11(2) |
| NIST 800-53B R5 (high) (source) | SR-11(2) |
| NIST 800-82 R3 LOW OT Overlay | SR-11(2) |
| NIST 800-82 R3 MODERATE OT Overlay | SR-11(2) |
| NIST 800-82 R3 HIGH OT Overlay | SR-11(2) |
| NIST 800-161 R1 | SR-11(2) |
| NIST 800-161 R1 C-SCRM Baseline | SR-11(2) |
| NIST 800-161 R1 Level 2 | SR-11(2) |
| NIST 800-161 R1 Level 3 | SR-11(2) |
| SCF CORE ESP Level 1 Foundational | MNT-07 |
| SCF CORE ESP Level 2 Critical Infrastructure | MNT-07 |
| SCF CORE ESP Level 3 Advanced Threats | MNT-07 |
US (6)
| Framework | Mapping Values |
|---|---|
| US FedRAMP R5 (source) | SR-11(2) |
| US FedRAMP R5 (low) (source) | SR-11(2) |
| US FedRAMP R5 (moderate) (source) | SR-11(2) |
| US FedRAMP R5 (high) (source) | SR-11(2) |
| US FedRAMP R5 (LI-SaaS) (source) | SR-11(2) |
| US IRS 1075 | SR-11(2) |
Capability Maturity Model
Level 0 — Not Performed
There is no evidence of a capability to maintain proper physical security and configuration control over technology assets awaiting service or repair.
Level 1 — Performed Informally
C|P-CMM1 is N/A, since a structured process is required to maintain proper physical security and configuration control over technology assets awaiting service or repair.
Level 2 — Planned & Tracked
Maintenance (MNT) efforts are requirements-driven and governed at a local/regional level, but are not consistent across the organization. CMM Level 2 control maturity would reasonably expect all, or at least most, the following criteria to exist: o Identify cybersecurity and data protection controls to appropriately address applicable statutory, regulatory and contractual requirements for technology asset maintenance. o Develop and disseminate formal guidance to facilitate a localized/regionalized process to implement secure and timely technology asset-specific maintenance operations, including preventative and reactionary maintenance operations.
- Technology asset maintenance is decentralized (e.g., a localized/regionalized function) and uses non-standardized methods to implement secure, resilient and compliant practices.
- IT/cybersecurity personnel:
- Maintenance controls are primarily administrative in nature (e.g., policies & standards) to manage change control processes associated with maintenance operations.
- Asset custodians develop and maintain formalized procedures to conduct controlled and timely maintenance activities throughout the lifecycle of the system, application or service.
- Maintenance operations may be centralized for certain locations (e.g., datacenters) and decentralized for other locations, both in terms of change management and execution.
- Facilities management uses a localized/regionalized process to facilitate the secure and timely implementation of non-IT maintenance operations, including preventative and reactionary maintenance operations.
Level 3 — Well Defined
Maintenance (MNT) efforts are standardized across the organization and centrally managed, where technically feasible, to ensure consistency. CMM Level 3 control maturity would reasonably expect all, or at least most, the following criteria to exist:
- IT/cybersecurity personnel develop and disseminate formal practices to implement enterprise-wide capability to conduct secure and timely technology asset-specific maintenance operations, including preventative and reactionary maintenance operations.
- Technology asset-related maintenance operations are centralized in terms of change management and governance. Local/regional practices fall under the broader enterprise-wide technology asset maintenance program.
- Facilities management uses an enterprise-wide process to facilitate the secure and timely implementation of non-IT maintenance operations, including preventative and reactionary maintenance operations. Local/regional practices fall under the broader enterprise-wide facilities management program.
- A Change Control Board (CCB), or similar function, centrally manages the process of IT and non-IT maintenance operations to reduce the chance of business interruptions from maintenance operations.
Level 4 — Quantitatively Controlled
See C|P-CMM3. There are no defined C|P-CMM4 criteria, since it is reasonable to assume a quantitatively-controlled process is not necessary to maintain proper physical security and configuration control over technology assets awaiting service or repair.
Level 5 — Continuously Improving
See C|P-CMM4. There are no defined C|P-CMM5 criteria, since it is reasonable to assume a continuously-improving process is not necessary to maintain proper physical security and configuration control over technology assets awaiting service or repair.
Assessment Objectives
- MNT-07_A01 system components requiring configuration control are defined.
- MNT-07_A02 configuration control over organization-defined system components awaiting service or repair is maintained.
- MNT-07_A03 configuration control over serviced or repaired organization-defined system components awaiting return to service is maintained.